Description ' At an informal meeting of the S.1 Working Group of the Satellite Experiments Coordinating Group fo the British National Committee on Space Research, held on 8 February 1960 at University College London.
Present; Mr M C Robins, Chairman; Dr R L F Boyd; Dr H Elliot; Professor J Sayers; Dr A P Wilmore

1. Visit to NASA January 1960
Dr Willmore outlined the results of discussion with NASA during the recent visit of 19-25 January 1960. A summary paper was being prepared. (see NCSP/20(60)), but salient points were:
NASA planned 8 development scout vehicles ; (6 rocket probes and 2 satellite launchings) of which the UK satellite would be the 9th scheduled firing, in September 1961
A sketch desing (ie all matters of principle decided) was needed by August 1960
Some features would be;
Orbit inclination 55 degrees
Minimum lifetime 6 months
Perigee 200 +/- 50 n. miles
Apogee 600 n. miles
Payload 150 pounds
Nominal cone diametere 25 inches
Maximum skin diameter at base 22.4 inches
Aerials 26 - 30 inches long; 4 in number, fed 90 degree out of phase
About 100 days would give complete scan of earth (within inclination limits)
Separation from final motor stage would be arranged
Structural design: some load taken by skin, batteries located aroung equator, electronics located centrally

2. Satellite Design
Professor Sayers thought it would be necessary to turn off the UCL probes during operation of his equipment. He would need 2 spheres, a few inches in diameter, preferable on separate stalks rather than on the NASA aerials, He would prefer an unpressurized satellit.

Dr Elliot would need a 5 inch cube in the "front" of the satellite to contain a 4 inch sphere

UCL would need Lyman - a and X-ray dtectors on the skin, with two additional probes.
Questions needing early consideration;
What power supply (battery or solar cell), and what telemetry and data storage are required?

What radio beacons and command links are necessary?

How should byt Birmingham/UCL switching be arranged?

What tracking and visibility requirement are important?


3. Organization
The combined US/UK Working Group will include;
Project managers US Dr Baumann, Goddard Space Centre, NASA; UK M.O Robins, UCL
UK representatives fromBirmingham University, Imperial College London, and University College London
US representatives for Telemetry, Coding and R.F
Structures
Power
Testing
Vehicle
Electrical layout
Operation Tracking, Launching,Telemetry and Data
Thermal Design
The Working Group would meet as required.

4. Next NASA Meeting
It was proposed that a meeting in Washington of the full US/uk Working Group should take place on 15 -16 March 1960. Questions needing discussion on that occasion would be:
What is angula acceleeration during satellite spin up period?
What environmental tests are required?

5. Date of next meeting
It was planned to hold the next meeting of the UK Group at 10.15 am n 29 February 1960 at UCL. '
Extent2p
FormatTypescript
AccessStatusOpen
Add to My Items

    Collection highlights

    Browse the records of some of our collections, which cover all branches of science and date from the 12th century onwards. These include the published works of Fellows of the Royal Society, personal papers of eminent scientists, letters and manuscripts sent to the Society or presented at meetings, and administrative records documenting the Society's activities since our foundation in 1660.

    The Royal Society

    The Royal Society is a Fellowship of many of
    the world's most eminent scientists and is the
    oldest scientific academy in continuous existence.
    Registered charity number 207043

    Website design ©CalmView



    CONTACT US

    + 44 207 451 2500
    (Lines open Mon-Fri, 9:00-17:00. Excludes bank holidays)

    6-9 Carlton House Terrace, London SW1Y 5AG

    Email Us →

    SUBSCRIBE

    Subscribe to our newsletters to be updated with the
    latest news on innovation, events, articles and reports.

    Subscribe →

    © CalmView